Sonatrach Seeks Contractors for Flare Gas Recovery at Skikda's RA1K Refinery as EU Methane Rules Loom

 


Sonatrach has launched an international tender for a flare gas recovery system at RA1K, its Skikda biggest domestic refinery, according to Algerian daily L'Algérie Aujourd'hui. The scope covers a detailed feasibility study, supply of recovery equipment and on-site installation, with technical bids due in February 2027. Sonatrach has not published a capacity target or budget for the project.

RA1K is the country's flagship refinery. Its processing capacity has reached 355,000 barrels per day and represents nearly half of Algeria's total refining capacity. algerie360

Why now: a long-running flaring target, not a regulatory deadline

The tender fits a flaring-reduction push that Sonatrach has described for several years. In 2023 the company's chief executive said flared gas recovery projects would help reach the goal of flaring below 1% in the medium term. The same plan named the Skikda and Arzew LNG plants among the sites for recovery projects, and noted that Hassi Messaoud had already cut its flaring rate to 2%. worldpipelinesmeed

The EU angle is more nuanced than it first appears. The EU Methane Regulation has applied since August 2024 and sets rules for measuring, reporting and verifying methane emissions, including transparency requirements for imports of fossil fuels. Its import rules concern crude oil, natural gas and coal, not refined products, so refinery flaring is not its direct target. The stronger link is reputational and commercial: Algeria's crude and gas exports to Europe will be judged on methane performance across the supply chain. brusselstimesbrusselstimes

The pressure has also eased for now. On 19 November, EU governments and Parliament agreed to delay the methane rules for oil, gas and coal importers by two years, double what the Commission had proposed. The Commission had put forward a one-year postponement on 14 October 2026, and Parliament had pushed for three years. The provisional deal still needs formal approval from both institutions. Parliament committees are due to vote on 23 November, followed by a plenary vote the same week. The agreement also requires the Commission to report on the regulation's application by 1 January 2028. EU gives oil and gas importers until 2029 on methane checks, rules out more delay +4

Algeria itself wanted more time. The US Department of Energy has said Algeria belongs to a coalition, now joined by Kazakhstan and Guyana, that called on the EU to delay and amend the regulation. So the Skikda tender is better read as long-term positioning than as a response to an imminent deadline. energy

What the economics could look like

Neither the tender nor the press report gives the recoverable volume, so any figure is an assumption. The scenarios below show the range, using the capex estimate of $18–35 million for a brownfield installation, an assumed $2.5 million a year in operating costs, and two gas valuations. The $8/MMBtu price is a conservative export-parity assumption, and $12/MMBtu is roughly the $70 per barrel of oil equivalent used in earlier estimates.

Recovery rateGross value at $8/MMBtuGross value at $12/MMBtu
3 MMSCFD~$8.8M/yr~$13.2M/yr
5.5 MMSCFD (~50,000 TEP)~$16.1M/yr~$24M/yr
10 MMSCFD~$29.2M/yr~$44M/yr

At the mid-range 5.5 MMSCFD, net of operating costs, simple payback comes to roughly 15 months at the higher price and about two years at the lower one. At 3 MMSCFD and $8, it stretches to three to five years or more. Payback of "12 to 18 months" is therefore achievable only with high recovery, a high gas valuation and the low end of capex.

Two further points. The value only materialises if recovered gas displaces gas that would otherwise be exported, rather than cheaper domestic fuel gas. And the climate benefit is smaller than headline figures suggest: recovered gas is still burned. The real gain is the methane that escapes unburned at the flare and the fuel gas displaced. A credible emissions figure has to wait for flow data from the feasibility study.

See Also :  Algeria’s Petrochemical Push: MTBE Nears Start-Up, Skikda Cracker Still Years Away

Who could bid

Sonatrach's approved-vendor lists for safety-critical refinery equipment typically favour established flare-gas and compression specialists such as John Zink Hamworthy, Zeeco, Honeywell UOP Callidus and Baker Hughes, though the tender documents do not name bidders. On the construction side, several contractors already know Skikda. Petrofac, Larsen & Toubro and Tecnicas Reunidas submitted bids on the RA1K hydrocracker package. Chinese firms are also active at the site: Sinopec companies won a 2022 contract for improvement work at the Skikda LNG plant, and Sinopec later won a contract for a new LNG storage tank at the GL1K plant. Sonatrach - Skikda Refinery Expansion +2

Execution risk

Skikda has a mixed record on delivery. Sonatrach first announced plans to expand the refinery in 2016, but the project's progress has suffered numerous setbacks. The hydrocracker was relaunched in March 2023 with an expanded budget. A flare recovery system is a smaller job, but it will involve sour gas treatment and tie-ins to a live plant, and procurement timelines in the sector have slipped before. meedmeed

Outlook

The tender is a sensible, low-regret investment. It can generate sellable gas, reduce flaring toward Sonatrach's stated target and strengthen Algeria's methane credentials with European buyers. How quickly it pays back depends on recovery volumes, gas valuation and contractor pricing, none of which will be known until the feasibility study and the February 2027 bids.